A job at Keswick Media is scheduled every 10 minutes, and occasionally a run takes longer than 10 minutes. The team wants to prevent a new run from starting while the previous run is still executing. Which job setting controls this?

  1. A.Task retry count, set to 0
  2. B.Run if condition, set to All succeeded
  3. C.Maximum concurrent runs, set to 1
  4. D.Auto termination, set to 10 minutes
Show answer and explanation

Correct answer: C. Maximum concurrent runs, set to 1

Why: The maximum concurrent runs setting limits how many runs of a job can be active at the same time; with a value of 1, a new run does not start while one is already in progress; it is skipped, or queued if queueing is enabled on the job. Retries control reruns of failed tasks, Run if conditions depend on upstream task results, and auto termination applies to idle clusters.